Correct Answer: (d) 9 days
Solution:A = 1/24, B = 1/16
LCM of (16, 24) = 48
A complete the work in one day = 2 units
B complete the work in one day = 3 units
They work together in 6 days = 6 × (2 + 3) = 30 units of work completed
Remaining work = 48 - 30 = 18 units
A alone complete the remaining = 18/2 = 9 days