Solution:According to the question,
8W × 3x = 4M × 6x
W = M
Therefore, (5M + 7W) = (5M + 7M) = 12M
12M × 0.75y = 18B × y
1M = 2B
Therefore,
(5M + 8W + 14B) = (5M + 8M + 7M) = 20M
Also,
(7M + 3W + 30B) = (7M + 3M + 15M) = 25M
According to the question,
20M × (z + 5) = 25M × (1.5z – 3)
4z + 20 = 7.5z – 15
z = 35/3.5 = 10
Therefore,
4M × 6x = 20M × (z + 5)
4M × 6x = 20M × 15
4M × 6x = 20M × 15
x = 12.5
Similarly,
4M × 6x = 12M × 0.75y
4M × 75 = 12M × 0.75y
y = 400/12 = (100/3)
Time taken by ‘A’ to complete the work = 1.2z = 12 days
Time taken by ‘B’ to complete the work = 12/0.75 = 16 days
Let the total work = 48 units
Efficiency of ‘A’ = 48/12 = 4 units/day
Efficiency of ‘B’ = 48/16 = 3 units/day
Work completed by ‘A’ and ‘B’ in 6 days = 6 × (3 + 4)
= 42 units
Let the efficiency of ‘C’ be ‘a’ units/day
Therefore, (a + 3) × 1.2 = 48 – 42
a = 5 – 3 = 2 units/day
Therefore, required time taken = 48/(4 + 2) = 8 days
Hence, option b.