Solution:Let the efficiency of a bull = ‘x’ units/day
Efficiency of a cow = ‘y’ units/day
And efficiency of a goat = ‘z’ units/day
Given that,
Amount of work completed by 3 bulls working together for 3 days = 3x × 3 = (3/16) of total work
Total work = 9x × (16/3) = 48x units
Amount of work completed by 2 cows and 2 goats working together for 8 days = (2y + 2z) × 8 = (48x/3) units
So, 16y + 16z = 16x
y + z = x
Amount of work completed by 4 goats working together for 24 days = 4z × 24 = (48x × (8/9)) units
Amount of work completed by 4 goats working together for (24 × (9/8)) = 27 days = 108z units
So, 108z = 48x
9z = 4x
Therefore, efficiency ratio of goat to that of bull is 4:9
So, z = (4x/9)
So, y = x – (4x/9) = (5x/9)
Therefore, efficiency ratio of cow to that of bull is 5:9
Let total work = 48 × 9 = 432 units
Then, efficiency of bull, cow and goat are 9 units/days, 5 units/days and 4 units/days, respectively.
Total work completed by 1 bull, 1 cow and 2 goats working together for 15 days = (9 + 5 + 8) × 15 = 330 units
Remaining work = 432 – 330 = 102 units
Time taken by 1 bull 1 cow and 1 goat to complete this work = 102 ÷ (9 + 5 + 4) = (17/3) days
Hence, option c.