31. The process of inspiring the subordinates to do a work or achieve an objective is called as: [RRB JE 29.08.2015 (Shift-I) ]

Correct Answer: (c) Motivation
Solution:

The process of inspiring the subordinates to do a work or achieve an objective is called as motivation.

32. Slack represents the difference between the– [RRB JE 29.08.2015 (Shift-II) ]

Correct Answer: (b) Latest allowable time and earliest completion time
Solution:

Slack represents the difference between the latest allowable time and earliest completion time.
• Event slack is defined as the difference between the latest event and the earliest event time.

33. Time and progress chart of a construction, is known as: [RRB JE (Chennai) 14.12.2014 ]

Correct Answer: (d) All of the above
Solution:

Bar chart or Gantt chart–It is graphical representation of activity versus time, usually horizontal axis represents the time duration and vertical axis represents activities.Milestone chart–It is also a graphical representation of activity v/s time. It is a improvement over the original bar chart.

34. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, then the expected time of activity is [JPSC AE (GEN. ENGG)-2013 ]

Correct Answer: (c)
Solution:

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, then the expected time of activity is

35. Which of the following are the guidelines for the construction of a network diagram? [JPSC AE (GEN. ENGG)-2013 ]

1. Each activity is represented by one and only one arrow in the network.
2. Two activities can be identified by the same beginning and end events.
3. Dangling must be avoided in a network diagram.
4. Dummy activity consumes no time or resource.
Select the correct answer using the code given below :
Code:

Correct Answer: (b) 1, 3 and 4
Solution:

Guidelines for the construction of a network
Activity–
A project can be broken in to various jobs in the form of operation and each operation consuming time or resource is called an activity.Event– It is an instant of time at which same specification milestone has been achieved. It denotes the start or completion of an activity.
Dummy Activity– It is an artificial activity represented by dashed arrows which neither consumes any time nor resources. It two or more activities having same set of successor and succeeding activities are having other predecessor as well, then two activities should emanate from a single node.
Two activates can not be identified by the same beginning and end event.
Dummy activities which shows predensor relations already implied by other activities are called as redundant dummies and can be removed.

36. Number of equations required to be analyzed in a given network by nodal analysis is equal to [MPSC AE PRE.- 23.06.2019 ]

Correct Answer: (d) One less than the number of nodes
Solution:

• Nodal analysis provides a general procedure for analysis circuits using node voltages as the circuit variables. It is a convenient method and reduces the number of equations to be solved simultaneously.
• Number of equations required to be analyzed in a given network by nodal analysis is equal to one less than the number of nodes
= n – 1
where, n = nodes

37. Gantt chart provides information about– [RRB JE 26.08.2015 (Shift-I) ]

Correct Answer: (b) Production schedule
Solution:

Gantt chart provides information about production schedule. It is the graphical representation of activity v/s time.

38. Total float is the amount of time that a task in a project network can be delayed without causing a delay to the [RRB S.S.E. 02.09.2015 (Shift-II) ]

Correct Answer: (c) Project completion date
Solution:

Total float is the time span by which starting or finishing of an activity can be delayed without delaying the completion of the project.
• It is maximum available time in excess to the activity completion time.
It is the difference between maximum time available and actual time required for the completion of the activity.

39. Which of the following is not a PERT event? [RRB JE 29.08.2015 (Shift-III) ]

Correct Answer: (d) Class is being attended
Solution:

In PERT technique, completion of an activity is called finish event or head event. A head event is that which has only incoming arrow.
• Attending class is a repetitive of work, hence it is would be CPM activity.

40. A term referring to the shortest possible time for which an activity can be schedule : [RRB S.S.E. 02.09.2015 (Shift-III) ]

Correct Answer: (a) Crash duration
Solution:

Crash duration is the absolute minimum possible time associated with the crash cost. Crash time impose the condition that the duration cannot be further reduced even after expending the extra resources to any extent.
Hence, direct cost for expediting an activity per unit time i.e., cost slope of an activity.