Estimation and Costing (General Engineering) (SSC JE)

Total Questions: 36

1. Labour and material for closing cavities at the jambs and sills shall be measured in_______. [JSSC JE (GEN. ENGG.) 04.11.2022]

Correct Answer: (a) m
Solution:

• Forming of cavity shall be measured in square meters stating width of cavity and shall include ties and their number per square meter.
• Labour and material for closing cavities at jambs, sills and heads of opening shall be described and mrasured separately in running meters.

2. What is the Unit of Payment for earthwork Excavation work? [JSSC JE (GEN. ENGG.)-23.10.2022 ]

Correct Answer: (b) Per m³
Solution:



3. The unit used for the measurement of roofing with asbestos or galvanized iron sheet roofing is: [JSSC JE (GEN. ENGG.)- 03.11.2022 ]

Correct Answer: (a) m
Solution:

4. Annual rental value is generally fixed at- [JSSC JE (GEN. ENGG)-2017 ]

Correct Answer: (c) 5 to 10% of value of building
Solution:

Annual rental value is generally fixed at 5 to 10% of value of building. The method of rent fixation is simply the reverse prouse of the rental method of value of a property. The rent is generally fixed based on a certain percentage of annual interest on the capital cost.

5. In analysis of rates, contractor profit is taken at the rate of [JSSC JE (GEN. ENGG)-2017 ]

Correct Answer: (c) 10%
Solution:

6. In a detailed estimate, the provisions for contingencies is usually [JSSC JE (GEN. ENGG)-2017 ]

Correct Answer: (b) 3% to 5%
Solution:

7. As compared to total cost of construction of a building, scrap value is taken as [JSSC JE (GEN. ENGG)-2017 ]

Correct Answer: (d) 10%
Solution:

Scrap value–It is defined as the value of an asset or property after being dismantled.
• It is generally taken to be 10% of cost of structure.
• Scrap value can be positive negative or zero.

Salvage value–It is the value of building at the end of its utility period without being dismantled.
• It can also be positive, negative or zero.

8. The first stage of a large construction work is [BPSC AE (GEN. ENGG.)-13.03.2022 ]

Correct Answer: (c) Conception
Solution:

Stages of construction projects–
• Conception
• Design
• Pre-construction stage
• Procurement stage
• Construction stage
• Post-construction stage
Conception–
• The concept of the project (planning and development) sometimes called project conceptin is the very beginning of the construction process.

9. The smallest basic unit of length in metric system is taken as [BPSC AE (GEN. ENGG.)-1995 ]

Correct Answer: (a) Millimetre
Solution:

The basic unit of length in metric system are–

10. Which of the following is the correct unit of measurement for the following item of work: 'brick work in foundation and plinth'? [NHPC JE (EE) 05.04.2022 (Shift-II) ]

Correct Answer: (b) Cubic metre
Solution:

The unit of measurement for brick work in foundation and plinth are cubic meter.
Brickwork–It depends on how the bricks are laid
• 4-inch brick work - it is measured in SQM or m²
• 8-inch brick work - it is measured in CUM or m³
• There should be nod deductions for small openings like pipe holes for scaffolding and openings less than 0.1 sqm.