Correct Answer: (b) 50 days
Solution:Total work of 50 men in 40 days = 50 x 40 = 2000 units
Since, 5 men left the work after each period of 10 days.
On the first 10 days, the work will be = 50 x 10=500 units
Next 10 days, the work will be = 45 x 10 = 450 units
Similarly, 10 days the work will be = 40 x 10 400 units
10 days the work will be = 35 x 10 = 350 units
So, the last 10 days, the work will be = 30 x 10=300 units
∴ The total time taken to complete the work
= 10 +10 +10 +10 +10 = 50 days