Work and Time (SSC) (Part-2)

Total Questions: 50

1. In a school sports camp, there is food provision for 200 students for 30 days. If 50 more persons join the sports camp on the 1st day then for how many days will the provision last ? [SSC MTS 18/10/2024 (Afternoon)]

Correct Answer: (a) 24
Solution:

2. A total of 24 men working 7 hours a day can complete a task in 10 days. In how many days will 21 men working 9 hours a day complete the same task ? [SSC MTS 21/10/2024 (Afternoon)]

Correct Answer: (d)
Solution:

3. 16 women can finish a task in 20 days and 20 men take 32 days to finish the same task. How many days will 8 women and 16 men take to finish the same task ? [SSC MTS 12/11/2024 (Afternoon)]

Correct Answer: (d) 20
Solution:

4. Rajesh, in his printing press, got an order to print some books, out of which he completed 17/27 of the order in 34 days. In how many days did he complete the entire order of printing? [SSC CGL 09/09/2024 (1st Shift)]

Correct Answer: (c) 54
Solution:

5. A and B can do a work in 12 days and 16 days, respectively. If they work together for 6 days, then the fraction of the work left is _______. [SSC CGL 19/09/2024 (2nd Shift)]

Correct Answer: (c)
Solution:

6. Varun and Raju, working together, can complete a job in 40 hours whereas Varun alone can complete the same job in 50 hours. The number of hours required by Raju to complete the job alone is: [SSC CGL 26/09/2024 (2nd Shift)]

Correct Answer: (a) 200
Solution:

7. A and B can do a work in 10 days and 40 days, respectively. How long will it take together to complete the work? [SSC CHSL 01/07/2024 (1st Shift)]

Correct Answer: (c) 8 days
Solution:

8. A and B can do a piece of work in 8 days and B alone can do it in 16 days. In how many days, can A do it alone? [SSC CHSL 01/07/2024 (2nd Shift)]

Correct Answer: (a) 16
Solution:

9. A and B can do a piece of work in 9 days and 15 days, respectively. If they work together, then the work will be completed in [SSC CHSL 01/07/2024 (3rd Shift)]

Correct Answer: (a)
Solution:

10. Fifteen persons working 12 hours a day earn ₹18,000 per week. How many rupees will 18 persons working 9 hours a day earn per week ? [SSC CHSL 01/07/2024 (4th Shift)]

Correct Answer: (b) ₹16,200
Solution: